Oakland Airport Connector, Oakland, USA
Oakland, USA
Project Start Date: November 2010
Planned Operations: 2014
Key Features:
- 5,100 m (16,732 ft) long APM system
- Bi-directional system
- Approx. 1,492 passengers per hour per direction
- Convenient service between Oakland's airport and a public transportation hub
- Pinched-loop arrangements and detachable grips
- Cost-efficient and environmentally responsible solution
- 20-year operations and maintenance contract for the system
|
Length |
5,100 m (16,732 ft) |
|
Configuartion |
Dual track pinched loop system with four trains |
|
Operating Speed |
50,4 km/h (31 mph) |
|
Headway |
280 seconds |
|
Dwell Time |
58 seconds |
|
Guideway |
Elevated steel guideway |
| System Capacity |
1,400 pphpd; ultimate system 1,900 pphpd |
|
Stations |
3 |
|
Trains |
4 three-car trains; ultimate system 4 four-car trains |
|
Train Capacity |
113 passengers per train (three-car train)
Ultimate system 148 passengers per train (four-car train) |
Links